Two separate projects to improve railway stations in Bradford have been delayed.
A £17.3 million project to upgrade Bradford Forster Square Station will not be completed until December 2021 - nine months after the original March 2021 completion date.
The £5.6 million refurbishment of Bradford Interchange is now not likely to be completed until October 2021, 13 months later than the initially proposed September 2020.
According to a report to be presented to members of the West Yorkshire and York Investment Committee, “insufficient expertise” at Bradford Council is behind the Forster Square project delays whilst a “shortage of resource” has halted progress on Bradford Interchange.
Stage set for return of Leeds Summer Series
Three jailed over Rochdale machete attack linked to crime feud
Police appeal to trace wanted Bradford man
Wakefield man convicted of manslaughter after pub incident
Nominations open for Blackburn with Darwen Community Volunteer Awards
Woman arrested after attempted robbery in Cheetham Hill
Bradford Council seeks inclusion in grooming gangs inquiry
Former care home worker jailed for 25 years over child abuse offences
Bradford man jailed for sexual assault on teenager
Culture at the Heart of Stockport’s Transformation
South Asian Art Exhibition Opens at Cartwright Hall
Men’s Mental Fitness Programme Launches in Blackburn
Remix Saturdays
Alim OnAir
Bhangra Nights
The Golden Era